Progress So Far

In July 2017, the SBCTA Board approved the I-10 Corridor Project's environmental document and the first phase of construction of the I-10 Express Lanes. 

2007: SBCTA initiated study of the I-10 Project.
August 2011: SBCTA started the study of Express Lanes.
January 2012: SBCTA began final technical studies and extensive public outreach.
October 2012: SBCTA conducted public scoping meetings.

July 2014: SBCTA Board selected Express Lanes as the locally preferred alternative.


November 2015: SBCTA Board reconfirmed the selection of Express Langes as the locally preferred alternative.




July 2017: SBCTA Board approves environmental document and construction of the first phase of I-10 Express Lanes.